Hypercare: the first 30 days after go-live

Go-live is not the end of the project. The first month is where a new Business Central system is either bedded in or quietly abandoned for spreadsheets. What normal looks like, what counts as a defect, and when to hand over to support.

The project plan has a milestone called go-live, and everyone treats it as the finish line. It is not. The first 30 days after go-live, the hypercare period, is where the system is either bedded in or quietly worked around, and the difference is almost entirely about how that month is run.

What hypercare is

Hypercare is a defined period, usually two to four weeks, in which the project team stays in place, on site or on call, with a faster response and a lower threshold for "we'll look at that" than normal support. It ends with a formal handover to business-as-usual support. It has a budget, a rota and an exit criterion, and it is agreed before go-live, not improvised afterwards.

What normal looks like

New users on a new system generate a lot of noise in week one, and most of it is not defects. A typical first fortnight for a 50-user business looks like this:

If days 11 to 20 look like days 1 to 3, something went wrong with the data or the testing, and hypercare needs extending rather than ending.

Defect, gap, or training?

Every ticket in hypercare is one of three things, and sorting them correctly is most of the job:

The daily stand-up (fifteen minutes, project manager, lead consultant, super users) sorts yesterday's tickets into those three buckets and agrees the day's fixes. The sponsor gets one line a day.

The things that go wrong in hypercare

Handing over to support

Hypercare ends when: the first month-end has closed and reconciled; there are no open showstopper or high-priority defects; ticket volume has been at business-as-usual levels for a week; the super users can answer the routine questions without the consultants; and the gaps list has an owner, a priority order and a budget. Then there is a handover meeting, a document that lists every open item and who owns it, and the support agreement starts: the response times change, the ticket route changes, and the project is formally closed.

Our support is two-hour response, and it starts from that handover, with the people who built the system still on the other end of the phone. If you are in a hypercare period that feels like it is not ending, talk to us; a day of senior time usually finds why.